McDevitt Senior Homes updates
End of June/beginning of July
Site fence installation scheduled for 6/29
Demolition of existing metal site fence, storage shed, miscellaneous loose items on 6/29
Rodent control installation scheduled for 6/30
Pre-excavation, 6/29 – 7/2
Tree and vine removal, 7/1 - 7/2
Pile drilling start scheduled for 7/6
Lead contaminated soil treatment will start in early July