McDevitt Senior Homes updates

End of June/beginning of July

  • Site fence installation scheduled for 6/29

  • Demolition of existing metal site fence, storage shed, miscellaneous loose items on 6/29

  • Rodent control installation scheduled for 6/30

  • Pre-excavation, 6/29 – 7/2

  • Tree and vine removal, 7/1 - 7/2

  • Pile drilling start scheduled for 7/6

  • Lead contaminated soil treatment will start in early July